中文

Automotive SPICE 4.0 · Process trace

Capability levels

An assessment assigns each process in the agreed scope its own level, from 0 to 5. “Level 2” means every process in that scope has reached 2. The processes in this pass are at 0. This page states what each level requires.

Back to ASPICE

What 0 through 5 ask

LevelThe questionWhat this repository can say
0The process purpose is not achievedA white box stops here. With no reading page, there is no result to discuss
1The purpose is achieved, and the work product existsAn opened process has only reached “there is a trace.” An incomplete trace cannot be called level 1
2The work is planned and tracked, and the work products are controlledThere is no process plan and no tracking record. Git only answers which commit a configuration item is
3The organization has a defined process, and the project follows itThere is no organizational process definition
4Data is used to predict and controlThere is no process measurement. A product-gate result is not a process measurement
5Improvement keeps the process changingWithout level 4, level 5 has no basis

Processes that already open

Each row names the trace that exists, and what is still missing before level 1 can even be discussed. Level 2 and above are not spelled out row by row: none of these processes has a plan or a tracking record.

ProcessTrace that existsStill missing before level 1
SWE.1Software requirements. They serve the safety goals. The goals are not the requirementsA record that these requirements were reviewed and accepted
SWE.2ArchitectureA record that the architecture was reviewed and accepted
SWE.3Middleware packagesA record that the detailed design was reviewed
SWE.4EM, OSAL, PHM, SM, Collector, and SIL-EM-01A record that these cases cover the detailed design
SWE.5SIL-EM-02, SIL-03, SIL-SM-01, SIL-01, SIL-06There is no component verification against the architecture. Only part of the purpose is achieved
SWE.6Trace. SIL-T4 answers SR-05. SIL-02 is the main-chain checkSIL-SM-01 is still to be refreshed, and SG-05 remains open. This is not recorded as fully passed
SUP.8Git baselineA configuration-management plan and a status account. At present it only identifies which commit
SUP.9Fix commitsA problem ticket, a cause, and a status. At present there is only the closing commit
SUP.10Commits on mainA change request and an approval. At present there is only the commit on main
MAN.3Phase table and the commit listAn estimate and a deviation log
MAN.5Five risks and their treatmentsAn owner and a review date
ACQ.4Upstream libraries, the list and one evaluation draftA periodic check of the suppliers
SPL.2The L3 release scriptOne release that was tagged and handed off. The CD script still only prints paths
PIM.3Devops commits record changes to the gate rulesAn improvement that came from a check or a measurement. At present a rule change is committed, and the improvement does not come from either

White boxes stop at the question of level 0

SUP.1 has no check of the process that is independent of development. MAN.6 has no process measurement, so levels 4 and 5 have no input. REU.2 has no reuse catalog. SUP.11, VAL.1, and SYS.1 through SYS.5 have no trace to open. The four hardware processes and the four machine-learning processes wait for a hardware manual and for the application algorithms.

This page does not assess SYS for the vehicle item, and it does not assess hardware or machine learning. The assessment records the scope and the gaps for this pass. The processes in this pass are at 0.

What would have to come first

In this order. No dates.

  1. Finish the part of each opened process whose purpose is not yet achieved. That is the condition for discussing level 1.
  2. Give each process that would enter the scope a plan and one tracking pass, and keep its work products on a baseline. That is the condition for discussing level 2.
  3. Levels 4 and 5 are not taken up yet. Until MAN.6 has a process measurement, those two levels have no input.