Automotive SPICE 4.0 · Process trace
Commits and gates
These processes share one GitHub history and the in-repo gates. Each section answers one question. Capability levels are explained on another page. In this assessment these processes are at 0.
SUP.8 · The configuration item
The configuration item is this repository. A baseline is one commit on main, identified by that git revision. Compose is generated from the commit that was checked out. To get one back, check out that commit and compose again. There is no separate configuration library.
Functional-safety assumption A-04 only requires evidence to be reproduced on the same compose output. That is an assumption, not this process.
SUP.9 · The closing record
A closed problem is a commit whose message says fix, not a ticket. Issues are enabled and empty. The closings that can be found are the commits that say fix, such as the gf-config wiring delete, the EM stub, and the GMT window. The message says what was repaired. The diff is the change. There is no separate cause analysis or status flow.
SUP.10 · Where the change is recorded
A change is one commit on main. The message says why. The diff is the impact. There is no separate change request and no approval ticket. Commits are pushed to main.
MAN.3 · The project phase
The scope is this platform middleware and its tools. Perception and planning in the repo are closed-loop loads used to run the gates. Progress is the commit list. The phases are listed in the roadmap draft, ROADMAP.md.
| Phase | Theme | State |
|---|---|---|
| P0 | Contract and the smallest loop | Closed |
| P1 | Vehicle communication, tools, OTA/DoIP skeleton | Skeleton closed |
| P2 | Multi-process SIL, observability | Closed |
| P2.5 | Host toolchain | Closed |
| P3 | Configurator, middleware, DoIP/OTA. Vehicle verification remains last | In progress |
There is no effort estimate and no deviation log. Standing is the commit list plus this phase table.
MAN.5 · Recorded risks
Project risks are the short list in the design draft. Each line has a treatment. There is no owner and no review date. Functional-safety assumptions stay on the assumptions page.
| Risk | Treatment |
|---|---|
| Three-stack complexity | Plugins, Event first |
| Processes split too fine | Decision table, colocated deploy allowed |
| OEM noise | Human review of the mapping, plus lint |
| Diagram and code drift | Tools read SOR only, CI checks |
| A multi-repo split too early | Monorepo first |
ACQ.4 · Upstream libraries taken in
The suppliers here are upstream libraries, not a vehicle OEM. The list is dep-manifest/DEPENDENCIES.yaml. The evaluation draft is THIRD_PARTY_EVALUATION.md. The policy is to pin a version, read the license, and build the board from source. Host apt is not the path that ships. There is no periodic supplier audit.
| Library | Where | Treatment |
|---|---|---|
| iceoryx | Board | P0, linked directly. Types must be relocatable |
| vsomeip | Board | P1. Boost size |
| CycloneDDS | Board | P1, profile can turn it off |
| RAUC | OTA | P1 evaluation. SWUpdate is out |
| rclcpp | Not on the board | ROS stays on the host |
SPL.2 · What constitutes a release
A release has to pass L3: bash devops/ci/scripts/smoke_release.sh. That run includes the toolchain, the DoIP path, T4, and the FuSa evidence pack. The pack lands in fusa/packs/afc/ and is not committed back by default. The T4 line is the product scene SIL-T4. It answers software requirement SR-05 and belongs to SWE.6.
| Layer | When | Entry |
|---|---|---|
| L0 | The main gate for a commit | devops/ci/scripts/smoke.sh |
| L0b | Extra when GMT, gf-config, or codegen changes. It blocks | smoke_toolchain.sh |
| L2 | Nightly: adds the DoIP path and FuSa SIL. No flashing | smoke_nightly.sh |
| L3 | Release: toolchain, DoIP, T4, evidence pack | smoke_release.sh |
There is no git tag and no GitHub Release. The CD script devops/cd/scripts/package_sil.sh only prints paths. It does not pack or upload.
PIM.3 · Change of the process itself
A change to the gates is a commit under devops. The current rule is written in devops/ci: release is the strictest; a toolchain change also runs L0b; DoIP runs on nightly and on release; flashing is not smoked. There is no separate improvement ticket.
Still only on the drawing
SUP.1 quality assurance has no check of the process that is independent of development. SIL-T4 is a product scene and belongs to SWE.6. MAN.6 has no process measurement. L0 through L3 are product gates, written in the release section above. REU.2 has no reuse catalog. The middleware packages are SWE.3, and how a third-party library is taken in is in the supplier section.
SUP.11 machine-learning data, VAL.1, and SYS.1 through SYS.5 have no commit or gate to open. The four hardware processes and the four machine-learning processes are the same: this item is platform software, and those two stretches wait for a hardware manual and for the application algorithms.