中文

Automotive SPICE 4.0 · Process trace

SWE.5 · Component verification

This stands at 0. The next step is a component-verification record. The trace already here: Integration scenes

Back to the assessment · Register

0 1 2 3 4 5

0 · Now

  1. The integration scenes already exist: SIL-EM-02, SIL-03, SIL-SM-01, SIL-01, and SIL-06. They answer integration verification after assembly.
  2. There is no component-verification record that names the component, the architecture behavior it keeps, and whether that behavior still conforms after assembly.
  3. The purpose of this level is not achieved. The level is 0.

Component-verification record

ComponentArchitecture behaviorConformity after assemblyVerification sceneVerification resultIdentifier of the record
No record yet

This table has no record yet. The next section is how to establish it. Integration scenes are not entered in this table. Register this table

1 · Next

  1. List the behaviors the architecture must keep, one behavior per row.
  2. Each behavior names the component that carries it. Several components are several rows.
  3. Assign a verification scene to the row: assemble first, then confirm whether the behavior still conforms.
  4. Conformity after assembly is Conforms or Does not conform. A nonconformity states the difference in the verification result.
  5. SIL-EM-02, SIL-03, SIL-SM-01, SIL-01, and SIL-06 stay with integration verification and are not entered in this table.

Component-verification record

ComponentArchitecture behaviorConformity after assemblyVerification sceneVerification resultIdentifier of the record
No record yet

This table has no record yet. The steps in this section say how to fill it. Register this table

2

  1. The verification plan names the component, the architecture behavior, where the scene lives, and who reads the result.
  2. The tracking record states whether each planned row is finished, and the verification result. An unfinished row stays.
  3. A row whose conformity is Conforms goes on the baseline, with the baseline identifier.

Verification plan

ComponentArchitecture behaviorWhere the scene livesWho reads the result
No record yet

This table has no record yet. The steps in this section say how to fill it. Register this table

Tracking record

Planned rowCompletionVerification result
No record yet

This table has no record yet. The steps in this section say how to fill it. Register this table

Baseline

Conforming rowBaseline identifier
No record yet

This table has no record yet. The steps in this section say how to fill it. Register this table

3

  1. Write the procedure for component verification, one entry at a time, including the completion criterion.
  2. For each entry, write how this item implements it.
  3. A nonconformity is its own row. A change to the procedure or to the implementation is another row, with its configuration identifier.
  4. The procedure and the conformity comparison share one configuration identifier.

Conformity comparison

Procedure entryImplementation on this itemConformityIdentifier of the comparison
No record yet

This table has no record yet. The steps in this section say how to fill it. Register this table

4

  1. Measurement comes from MAN.6. MAN.6 is outside this pass, so the table below stays blank.
  2. Before the work, write the expected result of component verification.
  3. After the work, write the actual result.
  4. When the result drifts, write the adjustment and its configuration identifier.
  5. A product-gate result is not entered in this table.

Process measurement

Expected resultActual resultDriftIdentifier of the adjustment
————

The cells stay blank. Process measurement comes from MAN.6, which is outside this pass. Register this table

5

  1. Take one drift from the level-4 process measurement.
  2. Change the procedure entry that corresponds to that drift.
  3. Name the measurement the change rests on.
  4. The changed procedure stays on the baseline and cites that measurement.

Procedure change

Procedure entry changedMeasurementChangeIdentifier of the change
————

The cells stay blank. Level 4 has no measurement, so this level has no record to rest on. Register this table